Grid services
Zuid-Holland, Netherlands
Zuidplas Grid Study
A constraint model for a node three developers had already written off. Two of the four options were viable.


Capacity
Study
Commissioned
2025
Grid connection
150 kV, TenneT
Programme
11 weeks
A node everyone had written off
Three developers had taken the published TSO figures at face value and moved on. We rebuilt the constraint picture from three years of measured nodal data and found two of four proposed configurations still cleared the threshold.
What the study is worth
Eleven weeks and a fixed fee, against a programme that would otherwise not have started. The client kept the model.
What went wrong
We were wrong about one of the two viable options; the developer built it anyway and it works.