Onshore wind

Jutland, Denmark

Havnsø Repower

Thirty-one machines down, nine up, and the farm produces more than it ever did.

A utility-scale solar array running toward distant hills at golden hour
Offshore turbines standing in calm water at dawn

Capacity

78 MW

Commissioned

2023

Grid connection

150 kV, Energinet

Programme

26 months

A foundations question, not a turbine question

Repowering is decided by what was poured twenty years ago. Seven of the nine positions reused their existing bases and access tracks, which is where the eleven months and roughly a fifth of the capital came from.

The two that did not

Late assessment found reinforcement corrosion in two foundations. Replacing them pushed the programme through a winter and we reported the delay before anyone asked.

What went wrong

Two of the reused foundations failed their assessment late, which cost a winter.