Onshore wind
Jutland, Denmark
Havnsø Repower
Thirty-one machines down, nine up, and the farm produces more than it ever did.


Capacity
78 MW
Commissioned
2023
Grid connection
150 kV, Energinet
Programme
26 months
A foundations question, not a turbine question
Repowering is decided by what was poured twenty years ago. Seven of the nine positions reused their existing bases and access tracks, which is where the eleven months and roughly a fifth of the capital came from.
The two that did not
Late assessment found reinforcement corrosion in two foundations. Replacing them pushed the programme through a winter and we reported the delay before anyone asked.
What went wrong
Two of the reused foundations failed their assessment late, which cost a winter.